Philippine Energy News

A collection of Energy Related News in the Philippines

Sunday, November 05, 2006

Gatchalian hits Mirant for refusing to provide power to Bataan plant

The Philippine Star 11/06/2006

Plastics king William Gatchalian is accusing the local unit of Atlanta-based Mirant Corp. of deliberately refusing to provide power to the recommissioned plant of Bataan Polyethy-lene Corp. (BPC), hindering the resumption of the plant’s operations.

In an interview, Gatchalian — a major shareholder in BPC — said the BPC has been recommissioned at a cost of $20 million and is ready to operate.

Unfortunately, he said the plant cannot resume operation because Mirant refuses to provide the plant with power, allegedly since the project will be controlled by Iranian investors.

Iran’s National Power Co. International is acquiring 60 percent of BPC, while Gatchalian, through his Metro Alliance Group, will hold 40 percent.

Gatchalian complained the problem has turned political, spawned by the long-standing conflict between the US and Iran. Mirant, being a US firm, allegedly refuses to deal with any firm that has Iranian investments.

However, Gatchalian pointed out, the buy-in by NPC International has not been concluded specifically because of the power problem.

The Iranian payment is already deposited in a Philippine bank, awaiting resolution of the power problem.

Gatchalian said while BPC can acquire power directly from the state-run National Power Corp., it would be costly since it must put up its own sub-station which would cost between $4 million to $10 million.

BPC is hoping to resolve the power problem so that it can resume operation by the first quarter of 2007 with an initial production capacity of 270,000 metric tons per year. BPC’s maximum production capacity is at 400,000 MT a year all for domestic consumption.

The Metro Alliance Group acquired in 2005 the shares of British Petroleum (38.5 percent), Malaysia’s Petronas (38.5 percent) and Japan’s Sumitomo Corp.(six percent) in BPC. Gatchalian is the majority shareholder of Metro Alliance.

BPC started operating in 2000 with a capacity of 200,000 MT.

Unfortunately, because of the global glut in petrochemical resin production, the local petrochemical players have been under a constant struggle to remain afloat.

The local petrochemical industry has been beleaguered that it had asked the government to delay a planned tariff reduction under the ASEAN Free Trade Area - Common Effective Preferential Tariff (AFTA-CEPT).

Plans to put up a naphtha cracker that would fully integrate the local petrochemical industry have remained on paper following the difficulties faced by the local petrochemical players and foreign proponents.

Read This

Capacity of wind power project to be scaled down

The Philippine Star 11/06/2006

The government is considering a reduction in the capacity of wind turbine generators to be put up in Ilocos Norte as it cannot afford the construction of the originally planned wind farm and transmission line.

During a meeting of the National Economic and Development Authority (NEDA) Investment Coordinating Committee (ICC), it said the plan to construct an alternative power plant was conceptualized over six years ago but was shelved because the project was too expensive.

In November 2004, the Philippine National Oil Co. - Energy Development Corp. (PNOC-EDC) bid out the project under two contracts but both exceeded the ICC-approved cost and available funding.

As a result, the government made changes on the proposed project such as reducing the power the generators can produce.

For example, the wind power project in Burgos, Ilocos Norte will only have a 30-megawatt (MW) nominal wind capacity instead of the planned 40 MW.

Also, the original project was supposed to have 42 kilometers of 230 kilovolts (kv) transmission lines that will interconnect the wind farm to the nearest power substation in Laoag City. But under the revised plan, it was reduced to a 115-kv single circuit.

Because of the delay, the project completion and commercial operation are now expected in January 2009.

The government needs to expedite the project because the expected electricity demand in 2007 will exceed supply. Should the project be completed on time, it would stabilize energy costs through reduction of use of imported energy.

Also, it would enhance the environment through the reduction of greenhouse gas by displacing a similar capacity thermal plant.

Read This